Crystallized Capillary Water Insulation Concrete Additive
PREPARATION of the MORTAR
For concretes to be insulated using SUTOP® B-21
Dosing at concrete plant:
SUTOP® B-21 may be added to the mixture with the mixture water as the final component.
Dosing at construction site:
SUTOP® B-21 is added to the mixer at a ratio of 2-3% and mixed for 3-5 minutes. Mixing shall be performed without delay.
30 kg drums
1 Year Shelf Life*
* If stored in its original package without opening the package under dry, frost free conditions
(1 week after opening the package.)